Here is what we've done so far:
- Put all hardware in place in data center
- Setup, configure and test backup solution
- Backup current data
- Set up Cluster
- Install database software (Oracle)
- Restore backup of current production data to new database
Our systems team is currently working diligently with the folks from Blackboard to ensure that our tasks are accomplished and testing is done by Friday afternoon. We will continue to keep you posted as the transition progresses.